May 8, 2018
Our Parking lot construction is well underway. Here are pictures and videos to follow the progress.
May 8, 2018
Subject: Christ The Good Shepherd Weekly Update 5-04-18
Team,
Here is a quick update on the project.
4/30/18 – 5/04/18
· Start paving Demo @ phase 1.
· Sawcut & demo @ K of C parking lot.
· Install temporary fence panels around phase 1.
· Remove fence at the playground.
· Start tree demo starting at the playground.
· Set-up office trailer.
· Set-up SWPPP.
[*] 5/07/18 – 5/11/18
· Cont. tree demo & haul off.
· Start excavation and installing storm sewer line starting from detention pond.
Subject: Christ The Good Shepherd Weekly Update 5-12-18
Team,
Here is a quick update on the project. See the attached project photos.
5/7/18 – 5/11/18
· Continue tree demo & haul off.
· Start excavation and installing storm sewer lines and installing M/H from the detention pond.
Subject: Christ The Good Shepherd Weekly Update 6-15-18
6/11/18 – 6/15 /18
Next Week 6/18/18 – 6/22/18
Team,
Here is a quick update on the project. See attached project photos.
9/10/18 – 9/14/18
1. Continue concrete pavement, sidewalk & utility demo & haul off in phase
2. Continue excavating and installing storm line, inlets & M/H in phase 2.
9/17/18 – 9/21/18
Continue excavating and installing storm line, inlets & M/H.
Start earthwork & stabilization.
Team,
Here is a quick update on the project. See attached project photos.
9/24/18 – 9/28/18
Excavate and install 24” RCP, type D-1 Inlet & PSET RC -type II at approaches.
Continue Hauling off underground utility spoils.
Continue cutting for subgrade.
Rain-out days this week are from 9-24-18 thru 9-27-18. 9-28-18 was a mud day.
10/1/18 – 10/5/18
Continue cutting for sub-grade. Stockpile sub-grade materials.
Blue top sub-grade.
Team,
Here is a quick update on the project. See attached project photos.
[*] 11/12/18 – 11/16/18
11/12/18 Monday was rained out.
Layout piers for light poles and the piers around the pond area.
Tie rebar cages for all piers.
Start installing edge forms and C/J.
Start fine grading at subgrade.
Pour concrete for all piers.
Start trenching and installing underground electrical for light poles.
Start trenching and installing underground irrigation sleeves.
Excavate grade beam around the pond.
[*] Next Week 11/19/18 – 11/23/18
Continue trenching and installing underground electrical for light poles.
Continue trenching for underground irrigation sleeves.
Continue installing edge forms.
Continue installing C/J.
Install Pavement rebar.
Continue fine grading subgrade.